Service Location, Vegetation Clearing and Minor Demolition, Stormwater Construction

20 August 2024

Works Notice #4 – Wednesday 20 August 2024

Works locations:

  • David Street – Vegetation Clearing and Minor Demolition
  • Village Green - Service Location, Vegetation Clearing and Minor Demolition
  • Porter Promenade and Campbell Street – Service Location

Cassowary Coast Regional Council wishes to advise that contractors RMS Engineering & Construction will be commencing the following works as part of the Mission Beach Town Centre Revitalisation:

Works: Service Location, Vegetation Clearing and Minor Demolition,

Stormwater Construction

Dates:Monday 26 August to Friday 20th September, some Saturday work required [subject to delays]

Work times:6am to 6pm

Description:Starting Monday 26 August, we will begin service location work in the Village Green. This will involve some minor demolition of paving, removal of garden beds, and clearing of vegetation to access the work areas. Additionally, vacuum excavation will be used to locate existing services. These steps are necessary to facilitate the installation of new stormwater infrastructure.

Service location will also be carried out at various locations along Porter Promenade and Campbell Street, and minor demolition and vegetation clearing will take place along David Street.

Temporary Impacts as a result of these works include:

  • Alternate traffic, parking and pedestrian movement will be in place
  • Parking spaces may be affected during service location works for construction access
  • Business access will be facilitated by the contractor
  • There will be no planned disruptions to services as a result of these works
  • Potential noise pollution due to machinery
  • Fencing will be in place for any open excavations, otherwise pedestrian areas will be reinstated where reasonable

Every effort will be made to reduce disruptions during this time, and we thank you for your patience and cooperation.

Please refer to the following maps to see the work area and contingency plans.

Village Green
Porter

For further information:

To speak with a construction engagement officer Hayley at RMS Construction on 0484 508 101 or email the project team at missionbeach@ccrc.qld.gov.au.

Summary of works

Start Date

Finish Date

Location

Description

22/7/2024

23/8/2024

David Street

Stormwater outlet construction

6/08/2024

16/8/2024

Pirate Den / Foreshore

Dismantle deck / foreshore rock carting

26/08/2024

20/9/2024

David Street

Service location [part of stormwater outlet construction]

26/08/2024

20/09/2024

David Street, Village Green, Porter Promenade

Service location, vegetation clearing and minor demolition

All dates are subject to delay pending weather conditions and unforeseen circumstances.