Works Notification #8 Removal of Existing Toilet Block

8 October 2024

Works Notice #8 – Monday 8 October 2024

Works location:

  • Village Green – Removal of Existing Toilet Block
  • Cassowary Coast Regional Council wishes to advise that contractors RMS Engineering & Construction will be commencing the following works as part of the Mission Beach Town Centre Revitalisation:

    Works: Demolition and removal of existing in toilet block in Village Green

    Dates: Monday 28th October to Friday 15th November 2024 [subject to delays]

    Work times: 6am to 6pm

    Description:

    Starting Monday 28th October, RMS will begin disconnecting services to the toilet block currently located in the centre of Mission Beach Village Green. The toilet block will be permanently closed to the public, however a portable toilet will be available in the car park along Campbell Street for public use.

    Following disconnection of services, RMS and contractors will commence the demolition of the existing toilet block, to enable stormwater and other works to take place as part of the Mission Beach Revitalisation Project. A new permanent facility will be installed at a later stage of the Project, anticipated in early 2025.

    Please refer to the following maps to see the work area and contingency plans.


    Temporary Impacts as a result of these works include:

  • Village Green will remain open to the public
  • There will be no planned disruptions to services as a result of these works
  • Potential noise pollution due to machinery
  • Temporary fencing will be in place while work is being undertaken
  • Every effort will be made to reduce disruptions during this time, and we thank you for your patience and cooperation.

    Summary of works

    Start Date

    Finish Date

    Location

    Description

    22/7/2024

    23/8/2024

    David Street

    Stormwater outlet construction

    6/08/2024

    16/8/2024

    Pirate Den / Foreshore

    Dismantle deck / foreshore rock carting

    26/08/2024

    20/9/2024

    David Street

    Service location [part of stormwater outlet construction]

    26/08/2024

    20/09/2024

    David Street, Village Green, Porter Promenade

    Service location, vegetation clearing and minor demolition

    16/09/2024

    Ongoing

    David Street

    Closure of David Street – Local Traffic Only

    30/09/2024

    15/11/2024

    Porter Promenade

    Clearing Works and Service Location

    Watermain installation

    28/10/2024

    15/11/2024

    Village Green

    Removal of Existing Toilet Block

    All dates are subject to delay pending weather conditions and unforeseen circumstances.