REVISED DATES - Stormwater Works Eastern Side
24 March 2025
Revised Dates Notice STORMWATER
WORKS LOCATION: Porter Promenade - Eastern side
This notice provides revised dates for the stormwater works on the eastern side of Porter Promenade. The project scope remains unchanged; however, due to recent heavy weather, work stages have been delayed as RMS await drier conditions and the arrival of resources from Townsville.
Revised Dates:12th March to 12th April 2025, weather and resources pending
Work times:6am to 6pm Mon – Fri [Saturday work 6am to 6pm, as required]
Works Breakdown:
Stormwater works will continue moving North on the Eastern side of Porter Promenade. This will involve an extension of site fencing along Porter Promenade to enclose the new work areas and large excavation activities.
Monday 24 March 2025 – 2 April 2025 Beachtown Complex Driveway Width Will Reduce
Fencing will move up to the entrance of the Beachtown Complex next to The Chippy. The Stormwater renewal works will commence with the car park driveway being carried out in two stages to maintain access. The work is expected to be completed by 2 April 2025.
Monday 24th March 2025: Dewatering Works
RMS will carry out dewatering work between Lot 45 and Café Johalia, along with preparatory work for the main stormwater project, starting from March 31, 2025
Monday 31st March 2025: Full Closure Lot 45 to South of Café Johalia
Construction fencing will be installed to facilitate excavation works, commencing on March 31, 2025. The driveway for Lot 45 will be closed for approximately 10 days and will reopen once the works are completed and it is safe for light vehicle access. As the construction progresses, the southern section of the fencing will be adjusted to maintain public access.
Monday 07th April 2025: Works outside Café Johalia
RMS plans to begin excavation work in front of Café Johalia on April 07, 2025. This will affect the current pedestrian access to the café, but alternative access will be provided before the construction fencing is set up. The excavation and stormwater works are expected to take up to two weeks to complete, weather pending.
Temporary Impacts as a result of these works
include:
- RMS will ensure that pedestrian access for businesses is maintained
- The Beachtown complex carpark will remain open with one-lane entry and exit. Traffic using the Carpark will need to exercise additional caution
- An alternate delivery bay has been created in the Village Green for accessing Beach town complex
- Full closure of Lot 45 driveway for the works and alternative car park on Campbell Street
- Current pedestrian access closure for Café Johalia
- There are no planned disruptions to services whilst these works are undertaken
- Please be aware of heavy machinery and noise impacts during these construction works.
- Site fencing and shrouding will be in place for safety reasons during the construction works.
Every effort will be made to reduce disruptions during this time, and we thank you for your patience and cooperation.
To speak with a construction engagement officer at RMS Construction contact 0484 508 101 or email the project team at missionbeach@ccrc.qld.gov.au.