News

Service location - stormwater outlet construction

12 August 2024

Works notice # 3 - Monday 12 August 2024

David Street - Service Location, Stormwater Outlet Construction

Cassowary Coast Regional Council wishes to advise that contractors RMS Engineering & Construction will be commencing the following works as part of the Mission Beach Town Centre Revitalisation:

Works: Service Location, Stormwater Outlet Construction

Dates:Monday 26 August to Friday 20th September [subject to delays]

Work times:7am to 5pm

Description:From Monday 26 August service location will commence on David Street involving vacuum excavation, traffic management and import of temporary pavement works.Service location is to find exact locations for various existing services as well as any obstructions such as tree roots.

These works form part of the construction of the stormwater outlet on David Street (refer Works Notice # 1).

Please refer to the following map to see the work area and contingency plans:

Temporary Impacts as a result of these works include

  • Alternate traffic, parking and pedestrian movement will be in place
  • Parking spaces may be affected during service location works for construction access
  • Business access will be facilitated by the contractor
  • Construction traffic may limit access to turning area
  • There will be no planned disruptions to services as a result of these works
  • Potential noise pollution due to machinery

Every effort will be made to reduce disruptions during this time, and we thank you for your patience and cooperation.

For further information:

To speak with a construction engagement officer Hayley at RMS Construction on 0484 508 101 or email the project team at missionbeach@ccrc.qld.gov.au.

Summary of works

Start Date

Finish Date

Location

Description

22/7/2024

23/8/2024

David Street

Stormwater outlet construction

6/08/2024

16/8/2024

Pirate Den / Foreshore

Dismantle deck / foreshore rock carting

26/08/2024

20/9/2024

David Street

Service location [part of stormwater outlet construction]