Supplementary Notice - Sheet Pile Installation

22 October 2024

Date: 22 October 2024

Cassowary Coast Regional Council wishes to advise that contractors RMS Engineering & Construction will commence Sheet Piling Works as per Works Notification #9.

Effectively from Tuesday 29 October 2024 to Friday 1 November 2024, RMS will be installing sheet piles around the A8 Pit location near Gifts for Every Occasion. This work will include intermittent noise and vibrations, impacting nearby businesses during this time.

A dilapidation survey will be conducted beforehand to record the current condition of surrounding buildings, ensuring any potential impacts from the works can be properly assessed.

Every effort will be made to minimise disruptions to the community and local businesses.

In preparation for the Sheet Pilling Works, Monday 28 October 2024 from 8am to 3pm, Marine Parade will be closed to all local traffic to allow heavy machinery (crane and trucks) to unload materials.

We apologise for any inconvenience this may cause and appreciate your cooperation as we work to revitalise the Mission Beach Town Centre.

Should you require further information, email missionbeach@ccrc.qld.gov.au.

This project is proudly funded by the Queensland Government’s Local Government Grants and Subsidies program in association with Cassowary Coast Regional Council.