Works Notice #10 - Campbell Street – Watermain Installation

2 December 2024

Works locations: Campbell Street – Watermain Installation

Dates:4 December to 18 December 2024, [subject to delays]

Work times:6am to 6pm Mon – Fri [Saturday work as required]

Works Breakdown:

Stage 1 – Wednesday 4 December 2024: Watermain works will take place on the southern side of the Porter Promenade / Campbell Street intersection. This will involve a partial road closure as excavation, installation of the watermain, and backfilling are carried out.

Stage Two - Thursday 5 to Tuesday 10 December 2024: Watermain installation will continue on Campbell Street, with a partial closure of the driveway access to the Post Office Complex car park. This will allow for the installation of the watermain and completion of backfilling.

Watermain installation work will continue with minor disruptions until 18 December 2024.

Please refer to the following maps to see the work area and contingency plans.

Temporary Impacts as a result of these works include:

  • Access to Campbell Street will remain open and managed by the current traffic light arrangement
  • During Stage Two Campbell Street driveway access will be reduced
  • Alternate routes for deliveries, and pedestrian movement will be implemented
  • The contractor will ensure that access for businesses is maintained
  • There are no planned disruptions to services due to these works
  • Please be aware of potential noise from machinery during construction
  • Fencing will be installed around any open excavations, and pedestrian areas will be restored wherever required

Every effort will be made to reduce disruptions during this time, and we thank you for your patience and cooperation.