Cassowary Coast Regional Council wishes to advise that contractors RMS Engineering & Construction will be commencing/continuing the following works as part of the Mission Beach Town Centre Revitalisation:

Overall Works:

  • Continuation of stormwater infrastructure installation on Campbell Street
  • Continuation of Village Green footpaths & landscape works
  • Continuation of the toilet block
  • Start of construction of the awning footings on Porter Promenade (Adjacent Sky Dive Building & Pirate Den)
  • Start of road construction to include kerb and asphalt installation along Porter Promenade, east side.

Work times:6am to 6pm Monday – Friday [Saturday/Sunday work as required]

Works in September will include:

Traffic & Site Changes:

  • Traffic on Porter Promenade will move to western side of Porter Promenade, and remain as one lane
  • David Street diversion lane (only open to local traffic) will be maintained by the Contractor, with traffic control devices
  • Pedestrian access diversions around The Pirate Den Bar and Grill & Ex Blues Bar, Porter Promenade for footing construction works
  • Campbell Street remains closed with a detour around the Post Office car park
  • Council car park on Campbell Street to remain open

Stormwater:

  • Stormwater works continuation both sides of Campbell Street

Awning:

  • Awning footing works will start along Porter Promenade, adjacent to the former Blues Bar and Pirate Den Bar & Grill, including work setup and in-ground footings.
  • Continuing construction of toilet block walls and interior, within the Village Green, with some changes to pedestrian access
  • Continuation of concrete footpaths in Village Green, with associated changes to local traffic flow & pedestrian access during construction

Toilet Block:

  • Continuing construction of toilet block walls and interior, within the Village Green, with some changes to pedestrian access

Pavement Works:

  • Continuation of concrete footpaths in Village Green, with associated changes to local traffic flow & pedestrian access during construction

Works Locations:

Please note that access and work areas may change regularly, and updates will be provided as required.

Please refer to the following map to see the work area and contingency plans:

Temporary impacts because of these works

  • Delivery vehicle bay will move as required to a new location on Porter Promenade
  • Alternate routes for traffic, parking, and pedestrian movement will be in place
  • Traffic lights will be in place
  • Some parking spaces will continue to be temporarily lost within the works location
  • Business access will be maintained by the Contractor
  • All residents and businesses affected by planned service disruptions will be notified two weeks in advance by the Contractor
  • Potential noise pollution due to machinery
  • Fencing will be installed around any open excavations, and pedestrian areas will be restored wherever required

Every effort will be made to reduce disruptions during this time, and we thank you for your patience and cooperation.

For further information:

To speak with a construction engagement officer please call RMS Construction on 0484 508 101 or email the project team at missionbeach@ccrc.qld.gov.au.